UMass Memorial Health – Harrington Hospital's Webster Campus will undergo new paving on its access road and parking areas.
Starting Date: April 20
Expected Duration: Four to five weeks (weather permitting)
To minimize disruption to traffic flow and maintain access to hospital services, the project will be completed in multiple phases.
We encourage visitors to check this page regularly for updates on project progress and any temporary changes to parking or access routes. We appreciate your patience and understanding as we complete these important improvements to our Webster facility.
Current Phase of Construction
Phase 7: Begins Saturday, May 30 (Weather Permitting)
The parking lot will remain open. Crews will work on one half at a time.
May 30–31: Crews will excavate and prepare the lot in two sections.
Starting June 1: Paving will begin and is expected to take about one week.
Public Safety staff, along with cones and signage, will help direct traffic during this final phase of renovations.